2023 Traffic Projects    
Intersection Tentative Start Detail/Completion Date
Sample Bridge Road May 2022 Tree Removal/Road Widening/Paving
    Phase 1 - Completed
    Phase 2 - Summer 2023
Trindle Road & Locust Point Road Anticipated 2022 Roundabout Installation
    Tentative 2025
Route 11 & Commerce Drive April 2022 Signal Improvements
    Tentative 2023
2023 Park Projects    
Project Tentative Timeline Detail/Completion Date
Paul Walters Park TBD Build Out / Create new park
    TBD