PACT One LLC will complete pipelaying operations along Sunset Drive by the middle of next week (June 1) and anticipates moving directly onto White Birch Avenue and Marble Street. PACT estimates a duration of approximately 3 weeks to completion for pipelaying operations within the White Birch Farm Estates area. Upon completion of work in these areas, PACT will immediately move to the Millers Gap Road side of the project, at which time the Millers Gap Road work will commence. For everyone’s safety, Millers Gap Road shall remain closed between Wertzville Road and Amity Lane to allow completion of pipelaying at greater depths in this area. Advance notice signs will be posted along Millers Gap Road on June 5th to advise of the proposed June 19th road closure and detour.