North I-81 Sewer Extension Project - UPDATE
September 18, 2023
The PACT One LLC (PACT) final pavement restoration is scheduled to commence the week of September 25th. The plan at present is to address the areas of Sample Bridge Estates (Wild Rose, Houston & Sample Bridge) with estimated duration to completion to be approximately 2-3 weeks at this end of the project. Pavement restoration shall progress northward from the aforementioned areas, eventually moving into Sunset Drive and White Birch Farm Estates. As work progresses PACT shall provide updates to keep everyone informed of the planned schedule and proposed areas of work.